Access Denied!!!

It appears that you are using a private browser which blocks some scripts necessary for this page to function properly. As a result, you may experience limited functionality or the page may not work at all.

To access this page, please consider using a different browser or switch to the standard version of Firefox.

Thank you for your understanding.

Access Full Project

Publicly Funded

Privately Funded

Bidding Soon

Documents Available

Addenda Available

Post-Bid

Post-Bid

Saving Project...

Full details on over 250,000 Projects including 2000 updated daily available to subscribers

March 16, 2023

April 17, 2023

January 12, 2024

Multiple Locations

Site Work

No Information to Display

$2,299,325.00

Public - City

img_map_placeholder

Multiple Locations, Fort Smith, AR

Subscribe to View Full Documents

The 17-10-C1 project includes approximately 6,300 linear-feet of 8-inch through 12-inch diameter sanitary sewer line by conventional open cut installation and pipe burst replacement. The 19-23-C1 project includes approximately 4,070 linear-feet of 8-inch diameter sanitary sewer line by conventional open cut installation and pipe burst replacement. For the Bidder's bids to be considered responsible, the Bidder must provide a separate bid for each project 17-10-C1 and 19-23-C1. The Owner intends to award both projects to a single bidder. Please refer to Specification 00200, Information for Bidders, Part 15. The owner reserves the right to waive any informalities or to reject any or all bids. This contract is subject to applicable labor laws including Davis Bacon (for contracts $10,000,000 or more), Project Employment and Local Impact reporting, non-discrimination provisions, wage rate laws and other federal laws including the Fair Labor Standards Acts of 1938. The Work Hours Act of 1962, the American Rescue Plan Act of 2021, and Title VI of the Civil Rights Acts of 1964 also apply. The Uniform Grant Guidance including Domestic Preference provisions 200.322 apply to this project. Registration and good standing in the System for Award Management (SAM) will be required prior to contract execution. Project is subject to 2 C.F.R. Part 180 (excluded parties both Contractors and Subcontractors) and Treasury's implementing regulation at 31 C.F.R. Part 19. Each bidder must deposit with his bid, security in the amount, form and subject to the conditions provided in the Information for Bidders. An Arkansas contractor's license is not required at the time of the bid submission, however, one must be presented by the selected contractor prior to contract execution. This publication was paid for by the City of Fort Smith Utility Department, and the cost of the publication is $ 830.65 per Arkansas Act 954 of 2021. The City of Fort Smith encourages participation of small, minority, and woman owned business enterprises in the procurement of goods, services, and construction, either as a General Contractor or Subcontractor. No bidder may withdraw his bid within 60 days after the actual date of the opening thereof. The City of Fort Smith is an Equal Opportunity Employer Male/Female.

9 Record(s)

Subscribe to Get All Contact Details

Trades

Division 00 - Lorem Ipsum

Division 00 - Lorem Ipsum

Lorem, Ipsum, Dolor, Sit amet
Subscribe to See All Trade Details

You’ve Reached the Free View Limit

Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.

Come back in [[refresh_days]] to get [[project_count]] more free projects.

Related Projects