Publicly Funded
Privately Funded
Bidding Soon
Documents Available
Addenda Available
Post-Bid
Post-Bid
Saving Project...
Full details on over 250,000 Projects including 2000 updated daily available to subscribers
August 24, 2023
October 23, 2023
June 7, 2024
To Be Determined
Paving, Renovation, Site Work
No Information to Display
$2,400,000.00
Public - City
To Be Determined, Bullhead City, AZ
Project Description: The improvements to be completed at the Section 10 WRP include the construction of a new headworks building which will contain Owner supplied precast influent channels, mechanical screens, conveyors and wash presses. The Contractor will be responsible for installation, testing and startup of the Owner supplied materials and equipment, as well as for furnishing and installing necessary materials and equipment to perform site excavation, installation of new yard piping, construction of concrete foundations, walls and floors, masonry block walls, a roof system, doors, hatches, grating, stairs, HVAC systems, odor control piping and treatment system, conduit for controls and electrical wiring, and electrical equipment. Work will involve connections to existing plant piping, protecting underground utilities, asphalt patching, replacing concrete curb and gutter and overall site restoration disturbed by construction and coordination with the Owner's supervisory control and data acquisition programmer. BONDS: Bid Bond: 10% Payment Bond: 100% Performance Bond: 100% LIQUIDATED DAMAGES FOR FAILURE TO ENTER INTO CONTRACT The successful bidder, upon failure or refusal to execute and deliver the Agreement, Bonds, and certificates required within ten calendar days from the date of the Notice of Award, shall forfeit to the Owner, as liquidated damages for the failure or refusal, its bid bond and shall owe the Owner the difference between its bid and the amount of the contract actually entered into with another party. Project Completion Date: 270 Calendar days or less after Notice to Proceed. Construction must be complete and new headworks placed into service by June 7, 2024. Technical questions regarding the substance of this IFB must be submitted in writing or by email and received no later than August 6, 2023. Only those plan holders registered with the City of Bullhead City will receive any modifications to the plans, specifications and bid documents and any notices that are issued during bidding. City of Bullhead City reserves the right to accept or reject any or all bids or any part thereof and waive informalities deemed in the best interest of the City. The work shall occur in the areas as shown on the Drawings which are within the site of the Section 10 Water Reclamation Plant (WRP). The plant is located west of Highway 95, at the end of Richardo Avenue in Bullhead City, Arizona. A. The Contractor shall, except as otherwise specifically stated in applicable parts of these Contract Documents, provide and pay for all labor, materials, equipment, tools, construction equipment, bypass equipment, temporary equipment, facilities, and services necessary for the proper execution, testing, and completion of the work. B. This project will provide the Owner with a new headworks building which will contain Owner supplied precast influent channels, mechanical screens, conveyors and wash presses for the removal and disposal of trash and debris prior to the water reclamation plants influent pump station and generally consists of the following major items of work: 1. Construction of a new headworks building consisting of site excavation, installation new yard piping providing connections to existing systems. 2. Installation of Owner supplied equipment and material consisting of precast influent channels, mechanical screens, conveyors and wash presses and equipment control panel. 3. Contractor procured and installed concrete foundations, walls and floors, masonry block walls, a roof system, doors, hatches, grating, stairs, HVAC equipment and ducting. 4. Contractor procured and installed odor control piping and treatment system. 5. Contractor procured and installed electrical conduit, wiring, equipment and power and control. 6. Grading and site work associated with the improvements in and around the new headworks building to control new drainage from the building and existing site drainage. 7. Protecting the existing plant water system and maintain its operation during construction. 8. Protecting the influent sewer main and maintain its operation until the new building is constructed and the new equipment is operational. 9. Bypass pumping to divert the entire flow of the Section 10 WRP away from the new headworks building in order to complete the improvements and make the necessary connections to the existing piping while maintain the operation of the plant water system via a temporary connection. 10. Connect the new equipment to existing plant power, SCADA and plant control systems. Coordinate with the City's SCADA provider for programming and startup of the equipment. 11. Other miscellaneous work as shown on the Drawings.
Trades
Division 00 - Lorem Ipsum
One Low Price
- One license and one market
- Details and key contacts on all bidding projects
- Organize your pipeline with a digital bid board
- Automatically match opportunities to your profile
- Saved searches deliver daily project leads to your email inbox
Starting At
- All Starter Product functionality
- One license and one market (additional available after purchase)
- Full access to bidding and planning projects' details, documents and contacts
- Comprehensive planholders list coverage on bidding projects
You’ve Reached the Free View Limit
Want to see more project and bidder data in your market? Check out our product options and see what works best for you and your business.
Come back in [[refresh_days]] to get [[project_count]] more free projects.
Related Projects
Bullhead City, AZ
Bid Date: Aug 07 2023
Bullhead City, AZ
Bid Date: Aug 22 2023
Bullhead City, AZ
Bid Date: Jan 27 2023
Bullhead City, AZ
--
Bullhead City, AZ
Bid Date: Nov 09 2023
Bullhead City, AZ
Bid Date: Sep 12 2024
Bullhead City, AZ
Bid Date: Sep 20 2024
Bullhead City, AZ
Bid Date: Sep 20 2024
Page, AZ
Bid Date: Aug 22 2023
Chinle, AZ
Bid Date: Aug 09 2023
Flagstaff, AZ
Bid Date: Aug 25 2023
Phoenix, AZ
Bid Date: Aug 21 2023
Yuma, AZ
Bid Date: Jun 11 2025
Flagstaff, AZ
Bid Date: Aug 17 2023
First Mesa, AZ
Bid Date: Aug 17 2023
Recently Viewed
--
--
--
--
--
--
--
--
--
--
The data you need to build the relationships you want. Try it free.
Sign up now to get free company and project data. No payment required.
You're one step away from industry‑leading commercial construction data.
What is your business type?
We have a wide variety of products that are purpose built for certain business types.
